Works Unlikely This Week

no-workAt 09:44 I sent an email to Mr Adrian M., Loss Adjuster from GAB Robins Ltd regarding the outstanding expenses.

At 10:37 I sent an email to Mr P.M., BRICS Contractor Manager from GAB Robins Ltd regarding the outstanding works and I proposed a schedule of works.

At 12:53 I sent an email to Mr Aaron M., regarding the council’s contract with the Zurich Insurance Plc.

At 13:52 I received a call from Ms Sarah J. from Zurich Insurance Plc regarding my complaint. She mentioned that the insurance prefers the works to finish and then talk about the total compensation for the whole claim.

She also mentioned that it is unlikely that there will be any works this week.

Accomodation extensionAt 14:39 I sent an email to Mr Adrian M. from GAB Robins regarding the accommodation arrangements between the 3rd and 17th March 2014.

Apparently very few vacancies left on the Premier Inn County Hall.

 

At 14:51 Ms Sarah J. from Zurich Insurance Plc sent me an email stating:

Further to our telephone conversation this afternoon, I can confirm that one of our senior technical consultants, Mr Gary D., will be in contact with you by the end of this week to book a visit to go through the list of outstanding issues and agree a plan of action, with timescales as necessary.

I’m waiting on an update in regards to the drying and getting the flooring in to your home so it can acclimatise. You’ll be advised as soon as there is more information on this.

As agreed, compensation is owed to you but we are going to look at this once everything has been completed to your satisfaction.

 

This entry was posted in Expenses, News, Zurich Insurance Plc. Bookmark the permalink.