Meeting with E. J. Taylor

At 14:30 I met with Mr Michael Cole, Project Manager and Neil Hayden, Contracts Manager. Both of them are working for E.J. Taylor & Son Ltd.

We discussed the outstanding issues, I saw them most of the problems and they gave me a DVD containing the footage of the toilet’s waste pipe inspection.

Finally they promised to send me the schedule of works with the definite days and time frame.  They expect the works to last for three weeks since the floor contractor will be available on the 28th April 2014 at the earliest.